LESCO Demand Notice Charges (2026): New Meter Installation Schedule & Fees
Whether applying for an independent residential meter in an existing house or electrifying a newly built commercial plaza, obtaining and paying your demand notice is the final prerequisite before meter installation.
Strict 30-Day Payment Deadline
LESCO demand notices expire automatically 30 calendar days from the printing date. Once expired, the sub-division system will not accept bank payment without a formal validity extension endorsed by the Sub-Divisional Officer (SDO).
1. What is a LESCO Demand Notice?
A Demand Notice is an official payment voucher issued by LESCO specifying the capital expenditure, equipment cost (energy meter and service cable), and security deposit required to energize a new electricity connection.
Demand notices are issued after the LESCO line superintendent conducts an on-site feasibility survey to calculate physical distance from the nearest Low Tension (LT) distribution pole and verify transformer capacity.
2. Estimated Demand Notice Charges (2026 Schedule)
| Connection Category | Sanctioned Load | Standard Fee Range | Distance Limit |
|---|---|---|---|
| Single-Phase Domestic (A-1) | Up to 5 kW | PKR 7,500 – 11,500 | Within 40 Meters |
| Three-Phase Domestic (A-1 TOU) | Above 5 kW (5–15 kW) | PKR 35,000 – 48,000 | Within 40 Meters |
| Single-Phase Commercial (A-2) | Up to 5 kW | PKR 14,000 – 18,500 | Within 40 Meters |
| Three-Phase Commercial (A-2 TOU) | Above 5 kW | PKR 45,000 – 65,000 | Within 40 Meters |
| LT Pole Extension Required | Any Load | + PKR 35,000 per pole | Beyond 40 Meters |
* Note: If premise distance exceeds 40 meters from existing infrastructure, additional capital costs for LT conductors and concrete poles are assessed on the notice.
3. Payment and Document Submission Workflow
Log in to enc.com.pk using your application tracking ID to download and print the formal 4-copy demand notice voucher.
Pay the designated sum at an authorized branch of National Bank of Pakistan (NBP), Bank of Punjab (BOP), or Habib Bank Limited (HBL) designated for your sub-division.
Obtain an official Wiring Test Report (Form 'A' & 'B') signed by an electric inspector or licensed electrical contractor confirming installation of earth ground rods and circuit breakers.
Submit the Consumer Copy and LESCO Office Copy of the paid challan alongside the wiring test report to the Sub-Divisional Office. Retain your stamped receipt copy.
4. Statutory Meter Installation Timelines
Under NEPRA Performance Standards (Distribution) Regulations:
- Single-Phase Connections (Standard LT): Meter must be installed within 15 working days of paid demand notice submission.
- Three-Phase Connections: Installation must be completed within 30 working days.
- Line Extension Required: If new transformers or poles are installed, LESCO has up to 45 to 60 working days to energize the supply.
Track Application Online
Track the approval status of your new connection or demand notice issuance on the official ENC portal.
New Connection Guide →